Sunday, May 14, 2006

Large cabinets and accent paint

In this picture you can see what will be some of the cabinets in the new area where we punched into the garage. You can also see the green and red accent paint colors.


  Posted by Picasa

Cabinet installation in progress

  Posted by Picasa

Friday, May 12, 2006

Saturday, April 15, 2006

Let there be lights!

As of yesterday, electrical rough-in is complete. The inspector came through and things look good. We are one day ahead of schedule.
Next week: Sheetrock.
Posted by Picasa

Information Center

Here's where the contractors keep track of everything that goes on. On this table are plans, permits, documentation, specifications, and more. Everything stays here all the time so it can be accessible by the subcontractors, our project manager, or inspectors.

 Posted by Picasa

Monday, April 10, 2006

Electrical has begun

Electrical work started today and will continue for the rest of the week. Nearly all framing is complete. If all goes well, drywall work begins next week.


Can lights.


Electrical in the half bath. Posted by Picasa